Part 2 – Visit at the construction site

What’s up with Sporda’s new premises in Värnamo? Is it on schedule? To find out, we had a chat with Sporda Nonwovens’ CEO.

Part 2 – Visit at the construction site

What’s up with Sporda’s new premises in Värnamo? Is it on schedule? To find out, we had a chat with Sporda Nonwovens’ CEO.

Jonas Rylander, CEO of Sporda Nonwoven, how is the new construction?
“Thanks for asking, it’s good. The machine hall is sealed, that is, the walls and roof are in place. Installation of ventilation, electricity and pneumatics is currently underway.”

Was it the machine hall that was supposed to be ready first?
“Yes exactly, focus was on getting the machine hall ready first as the premises will house the airlay line which was expected to arrive in October. Now, unfortunately, there have been delivery delays and as it looks right now, the machine will arrive sometime between mid-November and early December.”

What do the other building plans look like?
Phase 1 (Machine hall)
The building has a roof and walls. Installation of ventilation, electricity and pneumatics is underway

Phase 2 (Warehouse)
Building frames are in place and walls and roof are being assembled
Week 40 – Floor casting
The building is expected to be completed by the end of the year 2022

Phase 3 (Office)
No work has yet started, but construction is expected to start in October
The office is expteced to be completed in April 2023

Do you want to know more?
Contact Jonas Rylander,