Part 2 – Visit at the construction site
Part 2 – Visit at the construction site
Jonas Rylander, CEO of Sporda Nonwoven, how is the new construction?
“Thanks for asking, it’s good. The machine hall is sealed, that is, the walls and roof are in place. Installation of ventilation, electricity and pneumatics is currently underway.”
“Yes exactly, focus was on getting the machine hall ready first as the premises will house the airlay line which was expected to arrive in October. Now, unfortunately, there have been delivery delays and as it looks right now, the machine will arrive sometime between mid-November and early December.”
What do the other building plans look like?
Phase 1 (Machine hall)
The building has a roof and walls. Installation of ventilation, electricity and pneumatics is underway
Phase 2 (Warehouse)
Building frames are in place and walls and roof are being assembled
Week 40 – Floor casting
The building is expected to be completed by the end of the year 2022
Phase 3 (Office)
No work has yet started, but construction is expected to start in October
The office is expteced to be completed in April 2023